Sunfire-HyLink Alkaline

RWE – Three-Digit Megawatt Electrolysis

Status:
Procurement
PDF Export as of: Oct. 04, 2024 · Sunfire.de

RWE – Three-Digit Megawatt Electrolysis

About the case

Status: Procurement
Customer / Project Partners: RWE
Product: Sunfire-HyLink Alkaline
Use case: Hydrogen for Industry

Sunfire-HyLink Alkaline | 100 MW

  • 100 MW pressurized alkaline electrolyzer
  • Up to 1900 kg/h green hydrogen
  • Planned commissioning at the end of 2027
  • Lingen, Germany

Hydrogen for Industry

  • RWE installs 300 MW electrolysis capacity in Lingen as part of the GET H2 Nukleus initiative
  • Off-Shore windparks supply sustainable electricity to produce 5,6 tons of hydrogen per hour
  • Hydrogen delivered via pipeline to industrial off-takers such as refineries or steel works.
Elektrolyseanlage Sunfire für Großprojekt mit RWE, 100 MW

Sources: /presse/rwe-ag/2021-11-15-rwe-startet-investitions-und-wachstumsoffensive/ (rwe.com) Wasserstoff-Projekt GET H2 Nukleus (rwe.com) STA02-geth2-de.jpg (1681×995) (rwe.com) TIC01-kraftwerke.jpg (1600×1161) (rwe.com)

Images ©: RWE

Sunfire GmbH, Hauptsitz Dresden, Gasanstaltstraße 2, 01237 Dresden, Germany, +49 351 896797-0, www.sunfire.de, info@sunfire.de
Commercial register number: HRB 31154, place of jurisdiction: Dresden Local Court, VAT ID: DE 273782253
Nils Aldag (CEO), Christian von Olshausen (CTO)

Sunfire-HyLink Alkaline | 100 MW

  • 100 MW pressurized alkaline electrolyzer
  • Up to 1900 kg/h green hydrogen
  • Planned commissioning at the end of 2027
  • Lingen, Germany

Hydrogen for Industry

  • RWE installs 300 MW electrolysis capacity in Lingen as part of the GET H2 Nukleus initiative
  • Off-Shore windparks supply sustainable electricity to produce 5,6 tons of hydrogen per hour
  • Hydrogen delivered via pipeline to industrial off-takers such as refineries or steel works.
Elektrolyseanlage Sunfire für Großprojekt mit RWE, 100 MW

Sources: /presse/rwe-ag/2021-11-15-rwe-startet-investitions-und-wachstumsoffensive/ (rwe.com) Wasserstoff-Projekt GET H2 Nukleus (rwe.com) STA02-geth2-de.jpg (1681×995) (rwe.com) TIC01-kraftwerke.jpg (1600×1161) (rwe.com)

Images ©: RWE

  • »After Sunfire has already provided an electrolyzer for our pilot plant in Lingen, we are looking forward to continuing this collaboration as part of the GET H2 nucleus project. With Sunfire's electrolyzer, the GET H2 nucleus will reach its full production capacity in 2027. At the same time, we are expanding our technology portfolio with an alkaline electrolyzer in the three-digit megawatt range.”«
    Dr. Sopna Sury
    COO Hydrogen – RWE Generation