Dresden, June 21, 2023 | With the final investment decision, the consortium partners of Bad Lauchstädt Energy Park have given the final go-ahead for realisation of this innovative hydrogen project.
With this step, the Bad Lauchstädt Energy Park is going beyond the theoretical planning phase and moving on to physical implementation. Construction work that is due to continue for several years was officially commenced at today’s ceremonial ground breaking attended by Dr Reiner Haseloff (state premier of Saxony-Anhalt) and Michael Kretschmer (state premier of Saxony) as well as board members and managing directors of the consortium companies.
The project will bring production and storage as well as the transport and use of green hydrogen in Central Germany to within tangible reach. The consortium partners are together making a decisive contribution to driving forward the energy transition and structural change in the Central Germany region.
“It was not a matter of course that we took this step,” explains project lead Cornelia Müller-Pagel. “It took a lot of hard work, together with funding of EUR 34 million, to get the project off the ground in September 2021, and then we encountered one or two expected and unexpected challenges. So I’m particularly proud that we are now the first and only regulatory sandbox for hydrogen to go into the implementation phase, especially against the backdrop of still considerable regulatory and framework-condition uncertainties in the project environment,” she added.
The Bad Lauchstädt Energy Park project has not escaped the general price increases of the past few months. At the start of the project, an investment volume of approx. EUR 140 million was estimated across all stages of the value chain, but now it is EUR 210 million.
“These significant price increases have been a major challenge for the project. The willingness of the partners to nevertheless bear these increased costs in order to implement the Bad Lauchstädt Energy Park shows the great commitment of the consortium partners – starting with Terrawatt and through to Uniper, VNG Gasspeicher, ONTRAS, DBI and VNG – to the energy transition and their conviction that green hydrogen will play a major role in this,” said Cornelia Müller-Pagel with conviction.
With the passing of this milestone, two other players will also join the project: Firstly, the construction and operation of the electrolyser will from now on be shared between Uniper and VNG Handel & Vertrieb, and secondly, the consortium partners were able to attract TotalEnergies Refinery Central Germany as the first anchor customer for green hydrogen.
“Industry, with its very high energy requirements, faces particularly great challenges when it comes to decarbonisation. We are therefore delighted that in the future we will be able to supply the TotalEnergies refinery in Leuna with green hydrogen from the Bad Lauchstädt Energy Park and thus support decarbonisation of the refinery process. This is another important milestone not just in the context of the pro-ject partnerships, but also for us as a society and for our customers,” said Cornelia Müller-Pagel.
In addition, work on the 30 MW electrolyser built by Sunfire, which will take about two years, and on the gas transport pipeline that is to be converted, including the construction of a new airlock for introducing pigs to the network, will start shortly.
In 2024, the TotalEnergies refinery in Leuna will then be hooked up by means of con-struction of the first network connection to the future ONTRAS hydrogen network. Trial operation will start in early 2025, and from the third quarter of 2025 the pipeline is scheduled to transport green hydrogen from the Bad Lauchstädt Energy Park for use in the TotalEnergies Refinery Central Germany.
Thomas Behrends, General Manager, TotalEnergies Raffinerie Mitteldeutschland: “The refinery in Leuna is in-tensively working on various projects to reduce its carbon footprint significantly by 2030. This project is a first step that will enable us to purchase green hydrogen in large quantities in the future and to produce low carbon footprint products such as renewable fuels of non-biological origin, or e-fuels. It is fully in line with TotalEner-gies’ ambition to decarbonize all hydrogen used in its European refineries by 2030. Our ambition is to replace the gray hydrogen with low carbon hydrogen, representing a reduction of 3 million tons of CO2 per year by 2030.“
Terrawatt Planungsgesellschaft mbH Managing Director Falk Zeuner emphasizes: “The great efforts have paid off in several ways. On the one hand, we can now prove that, in our case, renewable energies are capable of assuming system responsibility, i.e. supporting or relieving the grid, through the large-scale coupling of wind and electrolysis. In addition, our project is now a good example of the saying: Where there’s a will, there’s a way! – Thank you for the manifold support also from politics and authorities.”
Uniper – CEO Uniper Hydrogen Dr Axel Wietfeld: “Today is an important milestone for the Bad Lauchstädt Energy Park. Uniper is proud to be actively shaping the energy transition in partnership with VNG AG, VNG Handel & Vertrieb, VNG Gasspeicher GmbH, ONTRAS, Terrawatt Planungsgesellschaft and with the scientific support of the DBI Group. The Bad Lauchstädt Energy Park is a flagship project: Green hydrogen is a future technology on our path towards decarbonisation of industry. In the Bad Lauchstädt Energy Park, the successful combination of generation, transport, storage, marketing and use of green hydrogen is being researched as central components for a safe, sustainable and cost-effective energy supply of the future – as we move towards a decarbonised hydrogen economy. With the final investment in the 30 MW project with Sunfire as a partner, Uniper is driving the local energy transition forward.”
VNG Handel & Vertrieb GmbH (VNG H&V) – Managing Director Stephan Haupt: “We are delighted to now be joining the project consortium for the joint venture and to be driving the project forward with our expertise and full commitment. Together with our joint venture partner Uniper, we are striving to further boost the roll-out of a decarbonised hydrogen economy with intelligent production and marketing of green hydrogen in the Bad Lauchstädt Energy Park and to provide our customers with green hydrogen of the highest quality and a reliable source of supply in the future.”
VNG Gasspeicher GmbH – Managing Director Bernd Protze: “One prerequisite for the success of the energy transition is the ability to store energy in large quantities. At the moment, storing green hydrogen is the only way to store renewable energy on an appropriate scale. We are proud to be taking the first step towards the large-scale storage of hydrogen together with our project partners. We see great potential for expanding storage capacities at the Bad Lauchstädt site in order to be able to offer needs-based storage products for the market roll-out of green hydrogen in the future.”
ONTRAS Gastransport GmbH – Managing Director Ralph Bahke emphasised: “Converting a natural gas pipeline is the cheapest and quickest way to transport hydrogen. Here in Bad Lauchstädt we are demonstrating for the first time that it works in practice. At the same time, we are creating a blueprint for all related processes for the upcoming conversion projects. The good cooperation with the responsible authorities in Saxony-Anhalt played a decisive role in this.”
DBI – Gastechnologisches Institut gGmbH Freiberg – Managing Director of the DBI Group Dr Jörg Nitzsche: “The intensive and target-oriented research work of recent years is now paying off. The results will now flow into the construction of the Bad Lauchstädt energy park for generation, storage, transport and use and will provide cru-cial momentum for realising the hydrogen economy. The intensive cooperation between industry, research and authorities is essential for the success of this project.”
VNG AG – Hans-Joachim Polk, Member of the Executive Board of VNG, stated: “With the investment decision, we have reached a decisive milestone for this groundbreaking project. For me, this is a great team success for the entire consortium. My thanks go to all the partner companies for this. For this project to be a sustainable success, we need the right framework conditions that increase investment security for further green hydrogen projects.
About the Project
The Bad Lauchstädt Energy Park is a production-scale regulatory sandbox or real-life laboratory for the intelligent production of green hydrogen and its storage, transport, marketing and use. As a regulatory sandbox for the energy transition, the entire value chain of green hydrogen is being tested on an industrial scale for the first time. A 30 MW electrolysis plant from Sunfire uses renewable electricity from the nearby wind farm to produce green hydrogen. Temporarily stored in a salt cavern specially created for this purpose, the green hydrogen can be fed into the hydrogen network of the chemical industry in Central Germany via a converted gas pipeline and used in the future for urban mobility solutions. The sandbox thus contributes to researching these future technologies relating to green hydrogen and bringing them to market maturity – for a technologically strong and future-oriented hydrogen-using region in Central Germany and successful intersectoral integration throughout the Federal Republic.
Sunfire is a global leader in the production of industrial electrolyzers based on pressurized alkaline and solid oxide (SOEC) technologies. With its electrolysis solutions, Sunfire is addressing a key challenge of today’s energy system: Providing renewable hydrogen and syngas as climate-neutral substitutes for fossil energy. Sunfire’s innovative and proven electrolysis technology enables the transformation of carbon-intensive industries that are currently dependent on fossil-based oil, gas, or coal. The company employs more than 650 people located in Germany and Switzerland.
For more information visit www.sunfire.de
Dresden, June 21, 2023 | With the final investment decision, the consortium partners of Bad Lauchstädt Energy Park have given the final go-ahead for realisation of this innovative hydrogen project.
With this step, the Bad Lauchstädt Energy Park is going beyond the theoretical planning phase and moving on to physical implementation. Construction work that is due to continue for several years was officially commenced at today’s ceremonial ground breaking attended by Dr Reiner Haseloff (state premier of Saxony-Anhalt) and Michael Kretschmer (state premier of Saxony) as well as board members and managing directors of the consortium companies.
The project will bring production and storage as well as the transport and use of green hydrogen in Central Germany to within tangible reach. The consortium partners are together making a decisive contribution to driving forward the energy transition and structural change in the Central Germany region.
“It was not a matter of course that we took this step,” explains project lead Cornelia Müller-Pagel. “It took a lot of hard work, together with funding of EUR 34 million, to get the project off the ground in September 2021, and then we encountered one or two expected and unexpected challenges. So I’m particularly proud that we are now the first and only regulatory sandbox for hydrogen to go into the implementation phase, especially against the backdrop of still considerable regulatory and framework-condition uncertainties in the project environment,” she added.
The Bad Lauchstädt Energy Park project has not escaped the general price increases of the past few months. At the start of the project, an investment volume of approx. EUR 140 million was estimated across all stages of the value chain, but now it is EUR 210 million.
“These significant price increases have been a major challenge for the project. The willingness of the partners to nevertheless bear these increased costs in order to implement the Bad Lauchstädt Energy Park shows the great commitment of the consortium partners – starting with Terrawatt and through to Uniper, VNG Gasspeicher, ONTRAS, DBI and VNG – to the energy transition and their conviction that green hydrogen will play a major role in this,” said Cornelia Müller-Pagel with conviction.
With the passing of this milestone, two other players will also join the project: Firstly, the construction and operation of the electrolyser will from now on be shared between Uniper and VNG Handel & Vertrieb, and secondly, the consortium partners were able to attract TotalEnergies Refinery Central Germany as the first anchor customer for green hydrogen.
“Industry, with its very high energy requirements, faces particularly great challenges when it comes to decarbonisation. We are therefore delighted that in the future we will be able to supply the TotalEnergies refinery in Leuna with green hydrogen from the Bad Lauchstädt Energy Park and thus support decarbonisation of the refinery process. This is another important milestone not just in the context of the pro-ject partnerships, but also for us as a society and for our customers,” said Cornelia Müller-Pagel.
In addition, work on the 30 MW electrolyser built by Sunfire, which will take about two years, and on the gas transport pipeline that is to be converted, including the construction of a new airlock for introducing pigs to the network, will start shortly.
In 2024, the TotalEnergies refinery in Leuna will then be hooked up by means of con-struction of the first network connection to the future ONTRAS hydrogen network. Trial operation will start in early 2025, and from the third quarter of 2025 the pipeline is scheduled to transport green hydrogen from the Bad Lauchstädt Energy Park for use in the TotalEnergies Refinery Central Germany.
Thomas Behrends, General Manager, TotalEnergies Raffinerie Mitteldeutschland: “The refinery in Leuna is in-tensively working on various projects to reduce its carbon footprint significantly by 2030. This project is a first step that will enable us to purchase green hydrogen in large quantities in the future and to produce low carbon footprint products such as renewable fuels of non-biological origin, or e-fuels. It is fully in line with TotalEner-gies’ ambition to decarbonize all hydrogen used in its European refineries by 2030. Our ambition is to replace the gray hydrogen with low carbon hydrogen, representing a reduction of 3 million tons of CO2 per year by 2030.“
Terrawatt Planungsgesellschaft mbH Managing Director Falk Zeuner emphasizes: “The great efforts have paid off in several ways. On the one hand, we can now prove that, in our case, renewable energies are capable of assuming system responsibility, i.e. supporting or relieving the grid, through the large-scale coupling of wind and electrolysis. In addition, our project is now a good example of the saying: Where there’s a will, there’s a way! – Thank you for the manifold support also from politics and authorities.”
Uniper – CEO Uniper Hydrogen Dr Axel Wietfeld: “Today is an important milestone for the Bad Lauchstädt Energy Park. Uniper is proud to be actively shaping the energy transition in partnership with VNG AG, VNG Handel & Vertrieb, VNG Gasspeicher GmbH, ONTRAS, Terrawatt Planungsgesellschaft and with the scientific support of the DBI Group. The Bad Lauchstädt Energy Park is a flagship project: Green hydrogen is a future technology on our path towards decarbonisation of industry. In the Bad Lauchstädt Energy Park, the successful combination of generation, transport, storage, marketing and use of green hydrogen is being researched as central components for a safe, sustainable and cost-effective energy supply of the future – as we move towards a decarbonised hydrogen economy. With the final investment in the 30 MW project with Sunfire as a partner, Uniper is driving the local energy transition forward.”
VNG Handel & Vertrieb GmbH (VNG H&V) – Managing Director Stephan Haupt: “We are delighted to now be joining the project consortium for the joint venture and to be driving the project forward with our expertise and full commitment. Together with our joint venture partner Uniper, we are striving to further boost the roll-out of a decarbonised hydrogen economy with intelligent production and marketing of green hydrogen in the Bad Lauchstädt Energy Park and to provide our customers with green hydrogen of the highest quality and a reliable source of supply in the future.”
VNG Gasspeicher GmbH – Managing Director Bernd Protze: “One prerequisite for the success of the energy transition is the ability to store energy in large quantities. At the moment, storing green hydrogen is the only way to store renewable energy on an appropriate scale. We are proud to be taking the first step towards the large-scale storage of hydrogen together with our project partners. We see great potential for expanding storage capacities at the Bad Lauchstädt site in order to be able to offer needs-based storage products for the market roll-out of green hydrogen in the future.”
ONTRAS Gastransport GmbH – Managing Director Ralph Bahke emphasised: “Converting a natural gas pipeline is the cheapest and quickest way to transport hydrogen. Here in Bad Lauchstädt we are demonstrating for the first time that it works in practice. At the same time, we are creating a blueprint for all related processes for the upcoming conversion projects. The good cooperation with the responsible authorities in Saxony-Anhalt played a decisive role in this.”
DBI – Gastechnologisches Institut gGmbH Freiberg – Managing Director of the DBI Group Dr Jörg Nitzsche: “The intensive and target-oriented research work of recent years is now paying off. The results will now flow into the construction of the Bad Lauchstädt energy park for generation, storage, transport and use and will provide cru-cial momentum for realising the hydrogen economy. The intensive cooperation between industry, research and authorities is essential for the success of this project.”
VNG AG – Hans-Joachim Polk, Member of the Executive Board of VNG, stated: “With the investment decision, we have reached a decisive milestone for this groundbreaking project. For me, this is a great team success for the entire consortium. My thanks go to all the partner companies for this. For this project to be a sustainable success, we need the right framework conditions that increase investment security for further green hydrogen projects.
About the Project
The Bad Lauchstädt Energy Park is a production-scale regulatory sandbox or real-life laboratory for the intelligent production of green hydrogen and its storage, transport, marketing and use. As a regulatory sandbox for the energy transition, the entire value chain of green hydrogen is being tested on an industrial scale for the first time. A 30 MW electrolysis plant from Sunfire uses renewable electricity from the nearby wind farm to produce green hydrogen. Temporarily stored in a salt cavern specially created for this purpose, the green hydrogen can be fed into the hydrogen network of the chemical industry in Central Germany via a converted gas pipeline and used in the future for urban mobility solutions. The sandbox thus contributes to researching these future technologies relating to green hydrogen and bringing them to market maturity – for a technologically strong and future-oriented hydrogen-using region in Central Germany and successful intersectoral integration throughout the Federal Republic.
Sunfire is a global leader in the production of industrial electrolyzers based on pressurized alkaline and solid oxide (SOEC) technologies. With its electrolysis solutions, Sunfire is addressing a key challenge of today’s energy system: Providing renewable hydrogen and syngas as climate-neutral substitutes for fossil energy. Sunfire’s innovative and proven electrolysis technology enables the transformation of carbon-intensive industries that are currently dependent on fossil-based oil, gas, or coal. The company employs more than 650 people located in Germany and Switzerland.
For more information visit www.sunfire.de